| Item | Design example |
|---|---|
| Market | U.S. residential 120/240 V split-phase applications |
| Battery configuration | 2 × 15.36 kWh MERITSUN LiFePO4 batteries |
| Nominal stored energy | 30.72 kWh |
| Backup architecture | Dedicated backup-load center shown as an example |
| Inverter | Split-phase hybrid inverter; final model requires project validation |
| PV array | To be confirmed from site information |
| Installation location | Residential garage shown as a design example |
| Evidence boundary | No runtime, customer load, SOC setting or commissioning result is claimed |
Homeowners often begin with one question: “How long will the battery run my house?” An installer cannot answer that question accurately until the backup boundary is defined.
A dedicated backup-load panel may include refrigeration, lighting, communications, selected receptacles and essential controls. Adding HVAC, well pumps, electric water heating, cooking equipment or EV charging can change both the required inverter power and the expected runtime.
The load panel turns a general request for “home backup” into a measurable circuit list.
A critical-loads panel limits backup operation to selected circuits. This can reduce simultaneous demand, make runtime easier to predict and prevent discretionary appliances from consuming the emergency reserve.
Whole-home backup may be possible in some projects, but it requires more than sufficient battery energy. The inverter, transfer equipment, service rating, surge demand and load-management strategy must all support the operating plan.
The phrase “whole-home backup” should not be used until the design team has reviewed the service and load schedule.
Many U.S. homes use 120/240 V split-phase service. Some loads operate at 120 V from either L1 or L2 to neutral, while larger appliances may use 240 V across both legs.
The site survey should identify:
A balanced design helps prevent one leg or one output limit from constraining the system before the stored energy is exhausted.
Two 15.36 kWh batteries provide 30.72 kWh of nominal energy. That number does not state how many kilowatts the system can deliver at once.
The inverter must be evaluated for:
The battery bank, inverter and backup-load panel must be designed as one system.
Use this planning formula:
Estimated runtime = usable battery energy × conversion efficiency ÷ average backed-up load
For example, if the operating strategy provides 24 kWh of usable energy after reserve and the backed-up circuits average 3 kW, the simple estimate is about eight hours before accounting for changing loads, temperature and other site-specific effects.
This is an illustration, not a MERITSUN performance claim. Final runtime must be validated with actual load data and commissioned settings.
Average household load can look manageable while a compressor, pump or motor creates a much higher starting demand. Installers should document both running and starting power for:
Where necessary, soft starters, circuit priority or automatic load management should be evaluated by the project engineer.
A battery used primarily for solar self-consumption may cycle differently from a battery reserved for outages. The design team should agree on:
These settings belong in the commissioning and handover record.
The concept image places two batteries beside the inverter and backup-load center in a garage. A real site review must verify:
The authority having jurisdiction and the selected equipment documentation determine the final installation requirements.
Before customer handover, the installer should document:
Only the results recorded during this process should be presented as project outcomes.
Provide the following information when requesting system support:
It depends on the average load, peak demand, inverter power, backup boundary, SOC reserve and available solar. The nominal energy figure alone cannot answer the question.
It defines which circuits remain energized during an outage and prevents nonessential loads from using the stored reserve. It can also make system sizing and customer expectations clearer.
Possibly, but the installer must verify continuous power, compressor starting demand, other simultaneous loads and the desired runtime. Battery capacity alone is not sufficient.
The complete architecture normally includes an approved inverter, protection, disconnects and transfer equipment. Connections must follow the selected manufacturers’ documentation and local requirements.
The installer should record the circuits and demand on each leg, then verify that the inverter and backup architecture can support the proposed distribution without exceeding output limits.
No. It is a MERITSUN solution concept used to explain the installation-planning process. It does not represent a named customer or measured project result.
At minimum: service type, inverter, PV capacity, load schedule, backup circuits, target runtime, installation location, required quantity and delivery schedule.
Send MERITSUN the project location, service type, inverter model, PV capacity, backed-up circuits, major motor loads, required runtime, installation environment and quantity for a preliminary configuration discussion.
Discuss Your Project with MERITSUN